University of Rochester
Middle Campus Chiller Plant
Rochester , NY
Completion: 2008
Size: 6,200 GSF
Cost: $17,000,000
This new 4,000 ton facility, Phase 1 of the central plant expansion,
is currently in the schematic design phase. This new plant will provide
a much needed capacity increase to support the prosperous growth on the
Medical Center campus. Situated on an existing parking lot adjacent to
Kendrick Road, the contemporary brick design will respond to the campus
context by incorporating cast stone accents, large expanses of glass,
and metal screens. The 6,200 GSF first level contains the chillers and
the pumps with the cooling towers located on the roof, screened for acoustical
and aesthetic concerns. The project will be constructed using a CM and
is budgeted at $17 million. The anticipated completion date is May 2008. |  |